And finally… what lies beneath Aberdeen’s Union Street

And finally... what lies beneath Aberdeen's Union Street

The construction team working on the £17 million transformation of Union Street in Aberdeen have revealed the hidden obstructions they have uncovered so far during the project.

Excavation work on the central section of the thoroughfare has encountered a series of unexpected underground obstacles which were completely uncharted. 

From historic tram infrastructure to unrecorded utility pipes and cables or deep, hidden manholes, these discoveries have presented significant engineering challenges for Morrison Construction Infrastructure, which is the main contractor for the Aberdeen City Council development, which is part of the £150m City Centre and Beachfront Masterplan.



One of the biggest hurdles for the team has been finding multiple layers of uncharted utility services buried beneath the road surface. These include clusters of electric cables, gas and water pipes, and other infrastructure that were previously undocumented on any maps or diagrams. More than 20 unrecorded clusters have been found so far across the site.

And finally... what lies beneath Aberdeen's Union Street

Uncovering these services means work cannot proceed as planned. Instead, gas, electricity and water organisations must be consulted and visit the site to determine whether the cables and pipes are still live and operational or redundant. 

Live utilities must be made safe or moved and redundant services removed. This process is complex and time-consuming, adding unavoidable delays to the project.



Among the more unusual finds was an unknown capped off concrete access shaft which led down to a 10m deep underground culvert.

And finally... what lies beneath Aberdeen's Union Street

Due to the risk of collapse, the access shaft could not be safely removed. The project team then had to devise an alternative engineering solution to redesign the new street drainage system around this major obstacle. 

In another striking historical find, workers uncovered old electric tram power cables encased in timber-framed wooden boxes, which had been waterproofed and insulated with bitumen. Electric trams began operating in Aberdeen in 1899.



Eight of these former tram power lines have been found running the length of the project site. The bitumen insulation, designed to protect against Aberdeen’s damp climate, highlights the durability and engineering ingenuity of the city’s historic tram network.

Further evidence of the tram system was also found, with old metal sleepers encased in concrete beneath the road surface throughout the site.

And finally... what lies beneath Aberdeen's Union Street

The site team also uncovered a 46cm diameter cast iron carrier pipe running the full length of the project area. Checks have been unable to confirm what the pipe was used for, but it is believed to be an old redundant water main, which then had to be removed to allow current construction to progress.



The presence of these unknown underground structures has impacted the construction programme, with time and resources having to be diverted to investigate, document, and, where possible, remove or work around them. 

Before work began, pre-construction checks were carried out on the site, which included liaising with utility companies to confirm the location of services while ground radar was used to scan for any unexpected obstacles and trial pit holes were dug to investigate further.

And finally... what lies beneath Aberdeen's Union Street

However, these checks cannot guarantee to locate everything and sometimes services will remain undiscovered until the main excavations begin on site.



The improvement works cover a 300m section of central Union Street and are divided into three 100m sections between Market Street and Bridge Street. Work began on the eastern section from Market Street and immediately started to find hidden obstructions.

Staff are currently working on the south pavement from Market Street and have encountered similar issues with one utility recorded on service maps, but another nine unrecorded services were then uncovered during excavations, including two gas pipes.

Given the challenges faced in the initial stages, the team have taken proactive steps to conduct advance excavation work in the western section of the site and deep trench investigations in the central section, helping to identify further potential clashes with uncharted utilities before the main construction phase began there. 

And finally... what lies beneath Aberdeen's Union Street

While the roadway was exposed, the construction team also took the opportunity to install the new main carrier drainage pipe and associated chambers, ensuring that future works could proceed more efficiently.

Rod Buchan, construction manager for Morrison Construction Infrastructure on the project, said: “Despite the challenges presented by these unexpected underground discoveries, the team remains committed to delivering the much-needed upgrades to Union Street Central.” 

Hub North Scotland is Aberdeen City Council’s delivery partner for the City Centre and Beachfront Masterplan.

Project director John Edwards said: “The project team went to great efforts before works started to determine what lay beneath the ground. However, there is always a possibility of finding these uncharted obstructions, which can be incredibly frustrating for the site team and can have an impact on progress. The team continue to work hard to minimise that for the shops and businesses.”

Share icon
Share this article: