Builders merchants forced to collect orders as driver shortage hits supplies

Haulage the lack of availability of drivers are now the major concerns affecting the distribution of building materials across the UK construction sector.

Builders merchants forced to collect orders as driver shortage hits supplies

In an update on product availability, the Construction Leadership Council (CLC) said some suppliers are asking builders merchants to collect their orders as they cannot get enough drivers to complete deliveries. Regional distribution is a particular issue, with some finding challenges arranging deliveries to Scotland and the South West of England.

The statement from John Newcomb, CEO of the Builders Merchants Federation and Peter Caplehorn, CEO of the Construction Products Association, who co-chair the CLC’s Product Availability working group, revealed: “Although the overall supply situation has not changed substantially, there has been a temporary easing this month, most probably due to a combination of the holiday period and some domestic customers delaying or cancelling projects due to higher costs or cost uncertainty.



“Timber, cement, roofing products, bricks, blocks, insulation, steel and cable management systems remain the products in shortest supply, while global shortages of semi-conductors are a cause for concern in the lighting and appliance sectors. Although product and material price inflation has slowed, indications are that it will be 2022 before prices stabilise, with some manufacturers still to implement double digit price increases to recover current and future cost inflation.”

The statement added: “The problem is not limited to our sector, and with similar haulage issues affecting a wider distribution network there is no short-term fix. The Department for Transport is engaging with the freight sector and hauliers to look at both interim and longer-term solutions, which require collaboration between government and the sector.

“Container shipping continues to affect imports. Key ports in China are suffering reduced capacity due to Covid, but the backlog extends beyond China throughout distribution centres worldwide. This is forecast to continue through the peak Christmas season into early 2022. With capacity at a premium, container prices remain high; however, these rates are not sustainable in the long term and when demand signals change, we are likely to see prices reduce.”

Looking forward, the group discussed the requirement for aggregates and other key products when HS2 demand is at its peak in 2022/23. Projected volumes are being shared with industry trade bodies, key suppliers and the CLC Product Availability Group to help provide greater clarity and confidence about the industry’s ability to deliver HS2 as well as all other projects. This is a particular concern for smaller builders, who have struggled to compete for supply during the current period of extraordinary demand.