MIXED USE and NON-RESIDENTIAL
Applicant: D & J Smith
Planning Authority: Angus
Details: Construction of general purpose farm building and associated hardstanding
Location: Fallaw Farm, Arbikie Inverkeilor, Arbroath
Agent: AJFitchet/Architect LLP, 24 South Tay Street, Dundee
Reference: 20/00831/FULL
Application Link
Applicant: The Ambassador Theatre Group.
Planning Authority: Edinburgh
Details: Demolition of the existing scene dock structure at the Playhouse Theatre, 18-22 Greenside Place, Edinburgh
Location: Playhouse Theatre, 18 - 20 Greenside Place, Edinburgh
Agent: Montagu Evans LLP, Fao Rachel Mushet, 4th Floor, Exchange Tower, 19 Canning Street, Edinburgh
Reference: 20/05360/FUL
Application Link
Applicant: Parabola Edinburgh Limited
Planning Authority: Edinburgh
Details: Proposed construction of two public realm structures and associated works at land at Lochside Way, Edinburgh
Location: Land Adjacent To Lochside Way, Edinburgh
Agent: Montagu Evans LLP Fao. Rachel Mushet, 4th Floor, Exchange Tower, 19 Canning Street, Edinburgh
Reference: 20/05325/FUL
Application Link
TENDERS
Contract Authority: Port of Leith Housing Association Ltd
Details: This cyclical painting programme will cover approximately 226no. properties built between 1980 and 2000 and 75no. pre 1919 tenement properties. All properties are located within the Leith and North Edinburgh area. The cyclical painting works include internal and external decoration of the common areas to a number of units owned by the association. Additionally, works will be carried out to a number of units where the Association provides factoring services or has offered serviced to private owners where it owns a majority within a common stair.
Location: Leith and North Edinburgh area
Contact: angela.morgan@polha.org.uk
Publication Date: 11/12/2020
Contract Authority: Scottish Prison Service
Details: This Contract is to appoint a competent and capable Contractor to replace the non-secure fob system at HMP Low Moss.
The Contractor shall replace the existing system with one which is compatible with existing fobs. The Works require to be completed by the 12th March 2021.
Location: Bishopbriggs
Contact: Jennifer.Cleworth@sps.pnn.gov.