Council negotiates £400k off Elgin High School construction costs

Elgin High School replacementConstruction work will finally begin on a new high school in Elgin within weeks, after Moray Council regained control of its soaring costs, the Press and Journal reports.

Councillors were dismayed last year after it appeared that delays which set the project back by months had sent costs soaring.

Contractors said stalling the scheme had added £1 million to its price tag, inflating it from £28m to £29m.

But during last week’s full council meeting, it emerged that officers had managed to negotiate the sum back down to just over £28m.



Following the costs agreement construction is due to start on site soon, with a turf-cutting ceremony scheduled for March 16th.

Council convener Allan Wright said: “I’d like to thank the officers for the amount of work they put into getting the costs down, any savings are extremely welcome.”

Moray Council’s head of lifelong learning, culture and sport, Graham Jarvis, spent weeks locked in tense talks with contractors and government funding gurus during which he managed to arrange the revised cost.

The authority will now have to contribute just £1.6m to the school’s construction, rather than the £2m previously feared.



The scheme is expected to reach financial close next week having been approved in February last year.

The council now aims to complete the first phase of the project by next October, which will include the creation of the new school and sports block complex.

The school will be handed over that month, and the second and third stages of the scheme should be finished by June, 2018.

The final works will involve the demolition of the current Elgin High School building, laying a 3G pitch, creating car parking areas and landscaping grass pitches.